§ 25-710. Completion of required construction.  


Latest version.
  • (a)

    Upon completion of all required improvements shown on the approved site plan, the developer shall submit six (6) copies of the completed as-built site plan or building location plat certified by an engineer, architect or surveyor. The "as built site plan" shall be submitted at least one (1) week prior to the anticipated occupancy of any building for review and approval for conformity with the approved site plan and the ordinance and regulations of Franklin County and state agencies. This requirement may be waived in cases in which no public facilities are required or where all public facilities are accepted by the agency which will operate the same and where no further useful purpose would be served by preparation of as-built plans.

    (b)

    Upon compliance with the terms of this division and the satisfactory completion of construction, the zoning administrator shall release all bonds which may have been furnished.

    (Ord. of 7-16-02(3))

(Ord. of 7-16-02(3))