§ 7-54. Stormwater pollution prevention plan.  


Latest version.
  • (a)

    The stormwater pollution prevention plan (SWPPP) shall include the content specified by Section 9VAC25-870-54 and must also comply with the requirements and general information set forth in Chapter 880 General Permit for Discharges of Stormwater from Construction Activities 9VAC25-880-70.

    (b)

    The SWPPP shall be amended by the operator whenever there is a change in design, construction, operation, or maintenance that has a significant effect on the discharge of pollutants to state waters which is not addressed by the existing SWPPP.

    (c)

    The SWPPP must be maintained by the operator at a central location onsite. If an onsite location is unavailable, notice of the SWPPP's location must be posted near the main entrance at the construction site. Operators shall make the SWPPP available for public review in accordance with Section II of the general permit, either electronically or in hard copy.

    (Ord. No. 12-02-16, 2-17-16)

(Ord. No. 12-02-16, 2-17-16)